Opened 15 years ago
Last modified 8 years ago
#333 closed flight processing
CEH07/04, flight day 102b/2010, Moorhouse — at Version 12
Reported by: | benj | Owned by: | |
---|---|---|---|
Priority: | alpha 4 low | Milestone: | 2010 data processing completion |
Component: | Archiving | Keywords: | |
Cc: | Other processors: |
Description (last modified by benj)
Data location: ~arsf/arsf_data/2010/flight_data/uk/CEH07_04-2010_102b_Moorhouse
Data arrived from ARSF via network transfer on 12th April 2010.
Scientific objective: Unknown (can't find application)
Priority: a4l, process hyperspectral as a3
PI: Andrew Wilson
Also Clare Rowland at CEH Lancaster (see contact details page for email)
Collected as a single collection with day 102a (Hellifield, #332) - information on the same logsheet, combined nav data, etc. Have split into two separate collections for processing.
Sensors:
- Eagle
- Hawk
- Leica LIDAR
- Camera (01/09/2010)
Change History (12)
comment:1 Changed 15 years ago by benj
- Description modified (diff)
comment:2 Changed 15 years ago by benj
- Description modified (diff)
Andrew has asked that we send him the raw hyperspectral data for this flight and he'll process them. We just need to do the applanix and the Lidar.
Andrew should send us back a copy of the data for archiving when he's done, but in case he doesn't I'm leaving it in the processing queue, it'll just stay at the bottom. If/when Andrew does return the processed data to us it can come off the queue.
comment:3 Changed 14 years ago by pmlvis12
IPAS navigation processing done.
comment:4 Changed 14 years ago by ella
POSProc failed to make an Sbet file for this project during applanix processing, when attempt was made error message read too many consecutive IIN measurment rejections. Needs someone to take a look.
comment:6 Changed 14 years ago by jb362
Camera awaiting delivery check.
comment:7 Changed 14 years ago by ella
Camera delivery check complete. Everything looks good; ready to deliver.
comment:8 Changed 14 years ago by jb362
Camera data delivered 01/09/2010.
comment:9 Changed 14 years ago by jb362
- Description modified (diff)
comment:10 Changed 14 years ago by emca
Starting LiDAR processing
comment:11 Changed 14 years ago by emca
LiDAR lines Moor2 and Moor4 had incorrect range settings during data acquisition resulting a hole in the data for these lines.
LiDAR data is ready for delivery check at
~airborne/workspace/CEH07_04-2010_102b_Moorhouse/delivery/20100930/CEH07_04
comment:12 Changed 14 years ago by benj
- Description modified (diff)
Gary says priority is a4 from before they were recorded as high/med/low. Process as a4l for now, since original PI has retired, we've had no other contacts chasing this and that way it won't push our processing schedule back.