Changes between Initial Version and Version 1 of Procedures/NewSeason


Ignore:
Timestamp:
Mar 9, 2011, 11:57:42 AM (14 years ago)
Author:
mggr
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Procedures/NewSeason

    v1 v1  
     1= Jobs to do before a new flight season starts =
     2
     3== Lever arms ==
     4
     5If required, perform a survey of the positions of the instruments relative to the GPS antenna.  We need sufficient information to compute the positions of:
     6 * the GPS antenna(s)
     7 * the LIDAR scanner (a measurement to the reference point on the case is sufficient)
     8 * the RCD camera (a measurement to the reference point on the case is sufficient)
     9 * Eagle
     10 * Hawk
     11 * TABI, CASI or any other imaging instrument that is installed
     12
     13In all cases, a measurement to a suitable reference point on the casing of the instrument, plus an engineering diagram of the instrument, is sufficient.  We have these diagrams for the Specim and Leica instruments.
     14
     15These values should be recorded at:
     16 *
     17
     18== LIDAR ==
     19
     20=== Boresight calibration ===
     21
     22Ideally we should use the Gloucester city calibration area as it has much more vertical relief.  However, at the time of writing (2011), the area is not yet fully ready.  Instead, we can use the Little Rissington site for the time being.
     23
     24
     25Just to add to what had been mentioned below, for the LiDAR calibration
     26can you also ensure the correct lever arm values are entered into the
     27flight planning software and check the scan encoder offset.
     28
     29The lever arm values we currently have are (xyz):
     30GNSS 0.019 -0.024 -1.692
     31IMU  -0.411 0.206 -0.192
     32User Frame -0.142 -0.001 -0.188
     33
     34In particular the User Frame values need to be correct as we have no way
     35of adjusting these after data collection.
     36
     37=== Scan encoder  ===
     38
     39The scan encoder measures the angle the mirror is at.  At the start of the season, we should check the "centre/nadir" position is unchanged.
     40
     41The procedure to check the scan encoder:
     42 * Start up the system on the ground (no GPS or installation required)
     43 * Run BIT mode
     44 * Turn off 'Position In' switch on the front panel
     45 * This will snap the mirror to the centre
     46 * Then read F4's tick column,it should show the real scan offset and it should be within ± 500 ticks from the -10800 value
     47 * Don't forget to switch on 'Position In' when you finish testing