Opened 13 years ago
Last modified 13 years ago
#404 assigned flight processing
GB11_01, flight day 165b/2011, Diddington
Reported by: | knpa | Owned by: | knpa |
---|---|---|---|
Priority: | whenever | Milestone: | 2011 data processing completion |
Component: | Archiving | Keywords: | |
Cc: | Other processors: |
Description (last modified by emca)
Data location: ~arsf/arsf_data/2011/flight_data/uk/GB11_01-2011_165b_Diddington
Data arrived from ARSF via network transfer on 15/06/2011
GB11_01 Scientific objective:
Detection of Archaeological Residues using remote sensing Techniques (DART). DART will develop a deeper understanding of the contrast factors and detection dynamics, particularly
within traditionally ‘difficult’ areas (for example clay and pasture). This will allow the identification of
appropriate sensors and conditions for feature detection.
GB11_01 Priority: Whenever
PI: Doreen Boyd
PI: Anthony Beck
Notes: Pilot study - low priority.
Sensors:
Camera (13/07/2011)
Eagle (13/07/2011)
Hawk (13/07/2011)
LiDAR (15/11/2011)
Change History (18)
comment:1 Changed 13 years ago by knpa
- Description modified (diff)
comment:2 Changed 13 years ago by emca
comment:3 Changed 13 years ago by emca
- Owner set to emca
- Status changed from new to assigned
comment:4 Changed 13 years ago by emca
No sync for eagle/hawk line 6
comment:5 Changed 13 years ago by emca
Eagle line 2 - no sync. Incorrect GPS start time in header file. Changed GPS start time in header file to match Hawk.
comment:6 Changed 13 years ago by emca
Hyperspectral data ready for delivery check
comment:7 Changed 13 years ago by emca
Camera ready for delivery check
comment:8 Changed 13 years ago by anch
Delivery checking hyperspectral
comment:9 Changed 13 years ago by anch
checking camera as well
comment:10 Changed 13 years ago by anch
Camera looks fine except perhaps "GB11_01" project code in readme is different to "GB11/01" in hyperspectral readme.
comment:11 Changed 13 years ago by anch
Project has been blocked because we're waiting for OS vectors
comment:12 Changed 13 years ago by emca
PI was happy to receive data without OS vector check. When the vectors arrive the data can be checked retrospectively.
Hyperspectral and Camera have been sent 13/07/2011. Disk was sent to David Stott @ Leeds as requested by PI.
comment:13 Changed 13 years ago by emca
Processed LiDAR data - ready for delivery check
comment:14 Changed 13 years ago by adbe
LiDAR delivery check:
- There is not a logsheet
- Maybe mention there is heavy cloud over some lines
Otherwise, ready to deliver
comment:15 Changed 13 years ago by emca
- Description modified (diff)
Added logsheet to delivery. Data drop out was due the presence of a water body to east side of the survey area.
Data sent to David Stott @ Leeds as requested by PI 15/11/2011.
comment:16 Changed 13 years ago by mark1
Hyperspectral hawk bad pixel files and XML files have been re-created and re-delivered to PI (via email). This corrects sample number in bad pixel text files and Eagle IFOV value in XML and extra comments included.
comment:17 Changed 13 years ago by adbe
Hyperspectral sct's
line | eagle | hawk |
1 | -0.02 | -0.05 |
2 | 2.35 | -0.06 |
3 | -0.07 | -0.07 |
4 | -0.01 | -0.38 |
5 | -0.09 | -0.08 |
6 | 0.51 | 2.43 |
7 | -0.03 | -0.07 |
8 | -0.01 | -0.06 |
comment:18 Changed 13 years ago by knpa
- Component changed from Processing: general to Archiving
- Owner changed from emca to knpa
Beginning archiving.
Starting Camera, Eagle and Hawk processing.