Opened 17 years ago
Closed 16 years ago
#75 closed task (fixed)
Acquire 2008 radiometric calibration
Reported by: | mggr | Owned by: | mggr |
---|---|---|---|
Priority: | immediate | Milestone: | 2008 data processing completion |
Component: | ARSF | Keywords: | |
Cc: | Other processors: |
Description
We need copies of the ATM, CASI, Eagle and Hawk calibration files as soon as possible in the year.
The expectation is that Chris MacLellan of FSF is going to calibrate the CASI (and Specim?) early Dec 2007.
Attachments (2)
Change History (10)
comment:1 Changed 17 years ago by mggr
- Priority changed from medium to immediate
- Summary changed from Acquire radiometric calibration to Acquire 2008 radiometric calibration
comment:2 Changed 17 years ago by mggr
Many repeated attempts to reschedule a calibration:
- Feb during engine replacements (failed due to lack of availability of bulbs?)
- No luck in March
- April attempted again (FSF unavailable?)
- Chris apparently lost another bulb and now believes it may be the power regulator (getting checked)
- Phil asked about using the Met Office integrating sphere at Exeter, but apparently this isn't likely to work out
- May, tried for end of May during plane downtime, FSF unavailable
- slim possibility of ~10 June (after steering committee), but might be tough to get FSF and in peak flying season (Kidlington suggests end of July may be better..)
comment:3 Changed 16 years ago by mggr
Very initial comparison of ATM vs Eagle data (mark1's) indicates the 2007 pre-season may still be better - probably need to redo ATM calibration.
comment:4 Changed 16 years ago by mggr
Discussed Specim radiometric calibration situation during Gary's visit (also showed him PML's facilities in addition to re-discussing access to the Met Office integrating sphere). Conclusions:
- push for a calibration in July/Aug or Aug/Sept (to align with LIDAR testing, to avoid taking a week of the flying season and to allow FSF time to schedule)
- raise at steering committee
- deliver data with 2007 calibration (stability of instruments unknown :/), with a promise to notify and redeliver if there's a problem when 2008 calibration becomes available
comment:5 Changed 16 years ago by mggr
Raised at steering committee. FSF trying to go for late July for another attempt.
comment:6 Changed 16 years ago by mark1
Comparisons between 2007 and 2008 ATM calibrations and Eagle have been done for 4 flight lines from 2 separate projects. Results can be seen in spreadsheet and images at ~arsf/calibration/2008/atm2007_2008_comparisons Also see attached spreadsheet and screenshot for overview.
Changed 16 years ago by mark1
Spreadsheet containing comparisons of averaged eagle spectra, 2007 and 2008 ATM
comment:7 Changed 16 years ago by mggr
Calibration data gathered at FSF Edinburgh 21-23 July! Starting to process it.
comment:8 Changed 16 years ago by mggr
- Resolution set to fixed
- Status changed from new to closed
Detailed report on the attempt at Reports. Short version - good enough for verifying the calibration, but too much non-uniformity in the sphere for a real calibration.
Closing this ticket as all future work will be on 2009 calibration..
Updates: