Version 1 (modified by mggr, 16 years ago) (diff)

--

Data collection status

This page describes the status of upcoming flights in the current (2008) flying season.

Note: the actual flight date is dependent on operational restrictions and the presence of suitable weather conditions. All data are collected on a "best endeavours" basis.

Please contact Gary Llewellyn (Science / operations coordinator) if you have any questions or concerns: gaew@… (01865 374 391)

Projects completed in 2008

Project Location PI Date of final data acquisition
GB07/04 Hayton / Millington Wood Peter Halkon 13/02/08
GB07/03 Mid-Wales Gemma Bell 18/02/08

For status on data processing for flights that have been flown, see this page.

Status of projects in the 2008 flying season

Project Location PI Status Data collection Comments
GB08/13 Lake Vyrnwy Mat Disney Priority First acquisitions planned for May Two acquisitions
GB08/08 Wytham Woods Richard Harding Priority Next opportunistic acquisitions in April (see CEH07/05) Multiple acquisitions
GB08/02 Delamere Forest Mark Danson Priority First LiDAR data planned for March Multiple acquisitions
GB07/07 Inverclyde Tim Malthus Partially supported Final acquisition planned for late June
GB08/12 Borth Bog Angela HarrisPriority Planned for August Single acquisition
GB08/19 London Martin WoosterHigh PriorityJuly/August Hindered by absence of the ATM||
GB07/12 Peak District Andrew Wilson & Martin Wooster Roll-over Hindered by absence of the ATM||
GB08/03 Peak District Richard Armitage Reserve listFirst acquisitions maybe in April Multiple acquisitions
GB08/18 UK Richard Stillman First acquisitions maybe in April Two acquisitions
GB08/17 Western GB Ross Hill Reserve listFirst acquisitions maybe in April Single acquisition
GB08/10 New Forest Ross Hill R* First acquisitions maybe in April Two acquisitions
GB08/05 Dee Estuary Alejandro Souza Reserve list
GB08/07 Alejandro Souza R*opportunistic
GB08/15 Eaves Wood Alan Blackburn Reserve listFirst acquisitions maybe in April
GB08/11 East Anglia Doreen Boyd May + June Two acquisitions
GB08/06 Peak District Julia McMorrow End of June/Start of JulySingle acquisitions in 2008
GB08/09 Trent & Idle valley Malcolm Lillie Reserve list September
GB08/16 River Feshie James Brasington Reserve list June/August
GB07/05 Estwaite/Windermere Andrew Tyler Roll-over Final acquisition may be in June
GB07/05 Loch Leven Andrew Tyler Roll-over Final acquisition may be in June
GB06/02 Frieston Shore Tom SpencerRoll-over Partially supported, requires LiDAR data
GB01/12 Ripon Anthony CooperRoll-over Partially supported, requires LiDAR data
GB06/08 Weardale Claire Flemming Roll-over
HY05/02 Ayreshire Graham Ferrier Roll-over
HY05/06 Glenogil/Pitlochry Mark Cutler Roll-over
GB03/01 Fiskerton-Barlings Jim Williams Roll-over
CEH07/04 Moorhouse/Ribblehead/Hellifield Andrew Wilson Roll-over Acquisition intended in June No simultanious fieldwork
CEH07/02 Stanlow Andrew Wilson Roll-over Acquisition intended in April/May/June No simultanious fieldwork
HY05/04 Thameshaven Andrew Wilson Roll-over Acquisition intended April/May/June No simultanious fieldwork

Special or specific considerations

Project Location PI Status Comments
IPY07/09 Iceland Tim Wright High Priority roll-overDepends on consisten good conditions in Iceland and will be supported from the UK.
ET07/01 & ET07/04 Ethiopia Tim Wright High Priority roll-over Not supported due to adverse conditions
GB07/09 Alps Martin Kirkbride Reevaluated and replanned for 2008
GB07/10 Alps Ben Broke Reevaluated and replanned for 2008
GB05/07 Severn, Stour & Thames Paul Bates Contingency project May be concluded/withdrawn
CEH07/05 Wytham Wood Andrew Wilson Repeat Project - partially supported 18/02/08 May be concluded/withdrawn, see GB08/08
GB05/13 Plymouth Peter Land Partially supported May be concluded/withdrawn
CEH07/01 Buckingham Andrew Wilson Partially supported May be concluded/withdrawn
GB06/07 Silverflowe Andrew Wilson Partially supported May be concluded/withdrawn

Atmospheric projects

Project Location PI Status Data collection Comments
GB08/01 Oxford to Haverfordwest Nigel Langford Reserve list October
NL08/01 Netherlands Hugh Coe Pilot 4 acquisitions in May
Pilot for VOCALS (CH08/01) Wales Geraint Vaughan End of March Participation in VOCALS is yet to be confirmed

Attachments (16)